Viaduct and elevated station construction on Metro Line 6, spanning the stations at Mahakali Caves, Saki Vihar Road, Rambaug and Powai Lake.
Line 6 runs from Swami Samarth Nagar through JVLR and SEEPZ to Kanjurmarg. Eagle Infra's package covers part design and construction of the viaduct together with elevated stations along the corridor.
The work spans the full civil cycle — pier foundations and columns, cast-in-place pier caps, a dedicated casting yard and batching plant, U-girder fabrication, night pours, and girder launch and erection.
Scope of Work
Part design and construction of viaduct and elevated stations, excluding architectural finishing and pre-engineered steel roof structures
Project Snapshot
- Location
- Swami Samarth Nagar–JVLR–SEEPZ–Kanjurmarg, Mumbai
- Sector
- Metro & Rail
- Status
- Ongoing